Testing :: in phases

Add to Delicious Digg this links to this post -

Was reading Matt's blog at Aroxo, and found an interesting little summary of how testing should be conducted before releasing a site live:

Test type

Description

How many people

Over-the-shoulder The main sticking points in the system. Where the system confuses users.
Start when functional testing at 80% readiness. Earlier with mock-ups also possible.
10-15
Task-driven testing How well the system stands up on its own.
Start when the major usability holes uncovered in OTS testing have been fixed.
Start with 20-30 keep growing invites to 100 or so
Goal-driven testing End-to-end flaws across the system.
Start when functional testing at 95% system readiness with a slick UI.
150-200
Beta testing The marketing points for the site, highlights future developments. If there are enough users it may also reveal performance issues
Start when the system is 99% ready.
250+ including members of the public